Industrial · 2017

Hutchinson Production Hall, Dębica

20,224 m² production and warehouse hall: 2.5 MVA MV service connection, 2×1600 kVA substation, 2,080 kW generator set.

Hutchinson Production Hall, Dębica

Project description

Scope and solutions

Production and warehouse hall with an office and staff section and site development for Hutchinson Sp. z o.o. in Zawada (Dębica commune) — 20,224 m², documentation 03.2017. External installations: 2.5 MVA MV service connection, 2×1600 kVA transformer substation, emergency power from generator sets rated 2,600 kVA/2,080 kW, site lighting, LV cable lines. Internal: power distribution, power circuits, socket outlets, busbar trunking, normal and emergency lighting, 20 kVA UPS, cable routes, lightning protection and earthing. ELV: FAS, CCTV, access control, I&HAS, server room with LAN, door entry systems, barrier control, telecommunications service connection with duct system. Reference letter from Biuro Projektów Lewicki Łatak (05.2018).

Reference letter: Biuro Projektów Lewicki ŁatakReference letter — Biuro Projektów Lewicki ŁatakHutchinson production hall and warehouse in Dębica — 20 224 m² · 2018

Contact

Planning a similar project?

Describe the building and the project stage — we will reply with a quote and a schedule within one working day.

Quick enquiry

Quote within one working day. Helpful: floor plans or the architectural design, the power balance, grid connection conditions (if any).

PDF, DWG, DXF, ZIP, JPG, PNG — up to 10 MB in total

    Talk to the designer

    Marek Łagodziński
    CEO · Lead Electrical Designer
    +48 604 152 533 · mlagodzinski@ekoelprom.pl

    Address

    EKO ELPROM Sp. z o.o.
    ul. Myśliwska 66/123, 30-718 Kraków, Poland

    ELV department

    Telecommunications design

    HVAC automation & BMS